13 Jan 2007: First team meeting.  Alan designated team captain.

15 Jan 2007: Web site, jaddinc.googlepages.com, published.

18 Jan 2007: Team meeting.  Discussion of MATLAB work and planning for coming week.  Submission of Innovative Directions Exercise to Professor Clifford.

23 Jan 2007: Submission of Customer Needs Exercise to Professor Clifford.  Brief team discussion held.  MATLAB coding nearing completion.  RF Circuit design drafts completed.  Parts to be ordered this weekend.

29 Jan 2007: RF parts ordered and shipped (3-day shipping). 

30 Jan 2007: Submission of Functional Specification Document (FSD) - Version 1 and Five Project Concept Alternatives Exercise to Professor Clifford.

1 Feb 2007: Team meeting.  Plan for First Design Review and Concept Generation and Selection Document.  Set new goals.

1 Feb 2007: Parts arrived (filters(2), mixer, amp) Still to order: LNA and  I/Q demodulator.

6 Feb 2007: Final RF parts ordered and shipped

7 Feb 2007: Matlab code finished and working.

8 Feb 2007: Submission of Concept Generation and Specification Document (CGS) - Version 1 to Professor Clifford.  Presentation of First Design Review.

14 Feb 2007: All parts have arrived.

15 Feb 2007: Submission of Task List to Professor Clifford. 

17. Feb 2007: First PCB fabricated. (Not the final design! Changes still to be made.)

22 Feb 2007:  Matched Filter completed. 

8 Mar 2007:  Second Design Review Presentation.

8 Mar 2007:  Final PCB design finished and submitted for fabrication from 4pcb.com (estimated shipping date 15 Mar)

 Goals 

15 Mar 2007:  AGC and Symbol Timing Recovery working.  Final PCB in hand.

22 Mar 2007:  Carrier Phase Recovery working.

22 Mar 2007:   PCB fully populated and ready for testing

29 Mar 2007:   Fully functional Front-end hardware